Roads of Serbia show progress on the Miloš Veliki highway.

The public company Putevi Srbije has released a video showing the progress of the construction of the Miloš Veliki highway section from Pakovraće to Požega. Engineer Vladimir Petrović highlights that over 86% of the work has been completed on the subsection connecting the Laz and Munjino Brdo tunnels. In the Laz tunnel, construction and electromechanical work have been completed, and functional system testing is expected to begin. In the Munjino Brdo tunnel, finishing works on the substructures and installations are being carried out. The work is proceeding according to plan, although the deadlines for